MEB 2ND FLOOR
Morehouse School of Medicine
Atlanta, GA
Square Footage: 30,000 SF
Completion Date: 2022
MEB 2nd floor laboratory was experiencing severe humidity issues with chilled beams dripping condensation on very expensive laboratory equipment . Building pressurization was not under following the design sequences. TSCx was able to resolve all the issues left behind by original commissioning firm.
TSCx commissioned the following systems:
• Mechanical Systems
• HVAC Controls Systems
OWNER: Morehouse School of Medicine
GENERAL CONTRACTOR: Turner Construction Company