MEB 2ND FLOOR

Morehouse School of Medicine 
Atlanta, GA
Square Footage: 30,000 SF
Completion Date: 2022

MEB 2nd floor laboratory was experiencing severe humidity issues with chilled beams dripping condensation on very expensive laboratory equipment . Building pressurization was not under following the design sequences. TSCx was able to resolve all the issues left behind by original commissioning firm. 

TSCx commissioned the following systems: 

• Mechanical Systems

• HVAC Controls Systems

OWNER: Morehouse School of Medicine 

GENERAL CONTRACTOR: Turner Construction Company 

ARCHITECT: Lord Aeck Sargent Planning & Design, Inc. 