MAIN TERMINAL & CONCOURSE T 

Hartsfield-Jackson Atlanta International Airport 
Atlanta, GA
Square Footage: 2.9M SF 
Cx Cost: $293,185.00 
Completion Date: 2017

TSCx commissioned the replacement of all HVAC systems in the Main Terminal and North Concourse T. This project was conducted while the airport remained open requiring both security and very tight safety procedures. The project resulted in overall energy efficiency, gains, and enhanced occupant comfort at the World’s Busiest Airport. All systems had to function on emergency power. 

TSCx commissioned the following systems: 

• Building Automation Controls

• HW & CHW Piping

• Steam Boilers

• Air Handling Units

• Rooftop Handling Units

• Lightning Protection

• Terminal Units

• Test and Balance Reports

• Switchgear

• Exhaust Fans

• Lighting

• Switchboard

• Existing Pumps

• SCADA

• Electrical Panels

OWNER: Atlanta Airlines Terminal Corporation ♦ Todd Butler, PM – 678.414.8285 – TButler@CPS-Atlanta.com

GENERAL CONTRACTOR: New South Construction ♦ 404.443.4000 ♦ John Kitchen – 404.787.8146

ARCHITECT: Heery International, Inc. ♦ 404.881.9880

HVAC CONTRACTOR: F&S Mechanical ♦ 678.364.8592