TSCx provided the commissioning for the Concourse C Midpoint Expansion project which was being completed in four phases: Phase 1) Civil, Phase 2) East Addition, Phase 3) Renovation of Existing Building, and Phase 4) West Addition. TSCx provided commissioning services for pre-functional commissioning and functional performance testing of the HVAC, electrical, fire alarm, and sprinkler systems.
TSCx commissioned the following systems:
• Rooftop Air Handling Units
• Exhaust Fans
• Test and Balance Reports
• HW and CHW Piping
• Switchboard
• Lighting Protection
• Terminal Units
• Pumps
• Electrical Panels
• Building Automation Controls
• Switchgear
• Sprinkler System
• Air Handling Units
• Automatic Controls
• Domestic Water Heaters
OWNER: Hartsfield-Jackson Atlanta International Airport, Department of Aviation ♦ Robert May – 678.458.1455
CONSTRUCTION MANAGER: Holder-Moody-Bryson-Benchmark ♦ Jonathan Tribo – 404.768.0116
ENGINEER: Ray Group Consulting Engineers ♦ 770.953.1443
HVAC CONTRACTOR: F&S Mechanical ♦ 678.364.8592